Inpex Starts Working on Early Assessment of Masela


The defining phase of the project

Inpex Masela Limited as operator of Masela Block commenced preparation of pre-end engineering (pre-FEED) review after receiving a warrant from SKK Migas. After the visit of the Minister of Energy and Mineral Resources (ESDM) Ignasius Jonan to Japan on May 16, 2017, it was agreed that pre-FEED was conducted with one production capacity option and one island as the location of the LNG plant.

The letter stated that the capacity of LNG is set at 9.5 million tons per year (million tons per annum / MTPA) and 150 million cubic feet per day (MMscfd) of piped gas production.

Vice President of Corporate Services of Inpex Nico Muhyiddin said that Inpex has started preparation for the study. In general, he calls the Inpex who holds a 65% stake in participation and Shell 35% wants the initial development and implementation of the project in a rational and economic economics manner. It was according to him in line with the wishes of the government. "Currently, Inpex has started prep pre-FEED work," he said.

The pre-FEED stage will be an important step to formulate a revision of the plan of development (POD). As is known, earlier revisions PoD conducted to increase LNG production capacity when still
Using a floating refinery scheme.

However, in March 2016, President Joko Widodo decided to change the LNG plant development scheme from floating to onshore. As a result, Inpex takes the time to initiate a PoD breaker in the new scheme. According to him, the acceleration of the process at the pre-FEED stage will affect the other stages after which the FEED and the final investment decision (FID).

From the ESDM Ministry data, if the project starts on schedule, Abadi Field could produce its first gas by 2026. "Pre-FEED will be an important step to formulate a revised POD to be submitted to the government," he said.

Deputy Minister of Energy and Mineral Resources Arcandra Tahar acknowledged that the assignment letter to Inpex as operator of Masela Block has been granted. However, he mentioned that there are still problems that need to be resolved before the project definition study begins.

Arcandra was reluctant to explain further what else to finish before the pre-FEED began. Inpex has already got a Letter to start pre-FEED. Ask the Head of SKK Migas. There is something we need to finish first, "he said after attending a meeting at the office of the Coordinating Ministry for Economic Affairs, Tuesday (30/5).

The new pre-FEED phase begins after it is known that LNG production capacity and pipe gas volume will be developed by Inpex Masela.

IN INDONESIAN
TAHAP PENDEFINISAIN PROYEK

Inpex Mulai Garap Kajian Awal Masela


Inpex Masela Limited sebagai operator Blok Masela memulai persiapan kajian prapendefinisian proyek atau pre front end engineering design (pre-FEED) setelah menerima surat perintah dari SKK Migas. Pasca kunjungan Menteri Energi dan Sumber Daya Mineral (ESDM) Ignasius Jonan ke Jepang pada 16 Mei 2017 telah disepakati bahwa pre-FEED dilakukan dengan satu opsi kapasitas produksi dan satu pulau sebagai lokasi kilang LNG.

Pada Surat perintah disebutkan bahwa kapasitas kilang gas alam cair (LNG) ditetapkan 9,5 juta ton per tahun (million ton per annum/MTPA) dan produksi gas pipa sebesar 150 juta kaki kubik per hari (MMscfd).

Vice President Corporate Services Inpex Nico Muhyiddin mengatakan, saat ini Inpex telah memulai persiapan kajian. Secara umum, dia menyebut lnpex yang menguasai saham partisipasi sebesar 65% dan Shell 35% menginginkan agar pengembangan awal dan pengimplementasian proyek pada cara keteknisan yang rasional dan memenuhi skala keekonomian. Hal itu menurutnya sejalan dengan keinginan pemerintah. “Saat ini, Inpex telah memulai persiapan pekerjaan pre-FEED," ujarnya.

Tahap pre-FEED akan menjadi tahapan penting untuk memformulasikan revisi rencana pengembangan lapangan (plan of development/POD). Seperti diketahui, sebelumnya revisi PoD dilakukan untuk menambah kapasitas produksi LNG ketika masih menggunakan skema kilang terapung. 

Namun, pada Maret 2016, Presiden Joko Widodo memutuskan untuk mengubah skema pengembangan kilang LNG dari terapung menjadi di darat. Alhasil, Inpex membutuhkan waktu untuk melakukan pembahan PoD pada skema yang baru. Menurutnya, percepatan proses pada tahapan pre-FEED akan berpengaruh pada tahapan lain setelahnya yakni FEED dan penyampaian keputusan akhir investasi (final investment decision/FID).

Dari data Kementerian ESDM, bila proyek dimulai sesuai jadwal, Lapangan Abadi bisa menghasilkan gas pertamanya pada 2026. “Pre-FEED akan menjadi tahapan penting untuk memformulasikan revisi POD yang akan disampaikan kepada pemerintah," katanya.

Wakil Menteri Energi dan Sumber Daya Mineral Arcandra Tahar mengakui bahwa Surat penugasan kepada Inpex sebagai operator Blok Masela sudah diberikan. Namun, dia menyebut masih ada permasalahan yang perlu diselesaikan sebelum kajian pendefinisian proyek dimulai.

Arcandra enggan menjelaskan lebih lanjut masalah apa lagi yang harus dituntaskan sebelum pre-FEED dimulai. Inpex sudah mendapatkan Surat untuk memulai pre-FEED. Tanya saja kepada Kepala SKK Migas. Ada yang perlu kita selesaikan dulu," ujarnya usai menghadiri rapat di kantor Kementerian Koordinator Bidang Perekonomian, Selasa (30/5).

Tahap pre-FEED baru dimulai setelah diketahui kapasitas produksi LNG dan volume gas pipa yang akan dikembangkan oleh Inpex Masela.

Bisnis Indonesia, Page-30, Wednesday, May 31, 2017