Monday, August 9, 2021

Pertamina Directly Steps on Gas Working on Rokan Block

    The Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas) stated that PT Pertamina Hulu Rokan (PHR) could immediately move quickly to work on the Rokan Block, including wells drilling after its management shifted from PT Chevron Pacific Indonesia (CPI)PHR officially holds the management of the Rokan Block starting August 9 at 00:01 West Indonesia Time (WIB).

Blogger Agus Purnomo in SKK Migas

    Deputy of Planning for SKK Migas Benny Lubiantara said the progress of the transfer of management of the Rokan Block until Saturday (August 7) ​​was quite good. The smooth transition of the management of the Rokan Block is important considering that the contribution of this oil and gas block to the national oil lifting is quite significant. 

    One of the activities that must be ensured continuity is the drilling of development wells in the Rokan Block. He explained, with the agreement that has been made, the drilling of the wells program by Chevron will continue until the management of the Rokan Block shifts to PHR.

The Rokan Block By Chevron

"As soon as August 9 arrives, PHR can also immediately step on the gas, because preparations for drilling have been carried out together at the beginning," he said.

    As of Friday (August 6), referring to SKK Migas data, Chevron has successfully drilled 103 wells. Furthermore, the technical and operational data migration can be completed after CPI and PHR sign the minutes. The management of contracts needed to support operations has also been completed, among others by mirroring previous contracts so that the goods and services needed have been contracted.

    The supply of electricity and steam is also safe after Pertamina signed a contract with PT PLN (Persero), including the procurement of gas for power plants. The licensing process and operating procedures have also been completely transferred so that they can be used by PHR. Environmental problems have also been agreed upon so that they can be resolved properly. Employment issues can also be resolved where most of the CPI workers are transferred to PHR.

    President Director of Pertamina Hulu Rokan (PHR) Jaffee A Suardin said, as of Saturday (August 7), the preparation for the transfer of management of the Rokan Block had reached 99.5% of which 9 transition programs had been realized.

"The transfer of management of the Rokan Block will be 100% and effective when it officially switches on August 9, 2021, at 00.01 WIB," he said.

    He is optimistic that he can maintain and continue to operate the Rokan Block after the operatorship shifts from Chevron to PHR. For the drilling program, PHR will drill 84 wells and take over the CPI drilling plan of 77 wells. So, in total, his party will drill 161 wells during August-December 2021.

"We will do our best to maintain and continue to carry out massive operational activities to increase oil and gas production so that we can meet the national target of 1 million barrels per day (BPD) in 2030," said Jaffee.

    Jaffee added that in the Rokan Block, PHR will later manage a working area with an area of ​​​​about 6,453 square kilometers (km2) with 10 main fields, namely Minas, Duri, Bangko, Bekasap, Balam South, Kotabatak, Farmers, Pematang, Petapahan, Pager.

Production Up

    Under the management of Pertamina, SKK Migas projects that the production of the Rokan Block will increase. This year, the Rokan Block's oil production is targeted at 165 thousand bpd with a realization of 160,646 thousand bpd or 97.4% of the target as of the end of June. Next year, SKK Migas projects the oil production of this block to increase to 175,180 thousand bpd. To maintain production, Benny hopes that Pertamina has a more massive drilling program.

"We hope that through drilling more massive wells later by PHR, the Rokan Block production target can be achieved, maybe even surpassed. And production will start to increase at the end of this year," he said.

    In addition to drilling, the implementation of an enhanced oil recovery (EOR) program with chemicals is also expected to boost the production of the Rokan Block. Referring to SKK Migas, so far, studies related to EOR activities with chemical injections can be completed more quickly, so that dynamic studies have also been successfully completed. His party targets the approval of the plan of development (POD) for this EOR activity to be obtained this year.

"The discussion on the subsurface aspect has been completed, by the end of this year, hopefully, the POD will be completed so that the progress is expected to be on schedule," said Benny.

 Investor Daily, Page-17, Monday, Aug 9, 2021

Five Oil and Gas Contractors Sign Joint Contracts for Procurement of Rigs

    A total of five oil and gas companies signed a joint contract to use the jack-up rig Soehanah to realize the target of drilling wells in their respective oil and gas blocks. In addition to speeding up drilling, joint procurement of these rigs will also save costs and ultimately make the realization of investment costs that must be returned (cost recovery) more efficient.

rig Soehanah

    The five companies that signed the Jack Up drilling Rig contract Provision are Medco E&P Natuna Ltd, Mubadala Petroleum, Petronas Carigali, Premier Oil Natuna Sea BV, and Kuwait Foreign Petroleum Exploration Company (KUFPEC), with PT Vantage Drilling Company Indonesia.

Blogger Agus Purnomo in Petronas Carigali Ketapang

    Head of the Supply Chain Management and Cost Analysis Division Erwin Suryadi appreciated the joint procurement of rigs by the five cooperation contract contractors (KKKS) this. The existence of a joint contract provides certainty of the well's drilling schedule. This will ultimately support the achievement of the targets of 1 million barrels per day (BPD) and 12 billion standard cubic feet per day/BSCFD by 2030.

"With this joint contract, the commitment to drilling 12 development wells, 1 workover well, and 5 exploration wells can be fulfilled," he said.

    Not only speeding up the drilling process, but joint contracts will also increase cost recovery efficiency. From the signed contract,

    Medco Natuna E&P achieved efficiencies of up to US$ 5 million and other oil and gas companies of US$ 3.5 million. In the future, he hopes that this joint contract can also be applied to other contracts.

"The strategy of using joint contracts, especially for rig equipment which is very expensive, is one of the strategies that will be developed in the future, especially in stimulating exploitation and exploration activities to support the increase in national oil and gas production in a sustainable manner," said Erwin.

    President Director of Medco E&P Indonesia Ronald Gunawan said that his party always made various exploration and production activities efficient. However, on the other hand, his party still prioritizes the safety aspect in carrying out operations.

"We are grateful for the support of SKK Migas, other KKKS partners, and partners so that this amendment can be carried out," said Ronald.

Blogger Agus Purnomo in SKK Migas

    The realization of Wells drilling that has not been optimal is one of the reasons why the oil and gas production target has not been achieved this year. Referring to SKK Migas data, until last June, the realization of drilling development wells was still 186 wells from the target of 616 wells. 

    Furthermore, the realization of rework (workover) wells was 309 wells or 50% of the target 615 wells and the realization of drilling exploration wells was only 13 wells or 27% of the target 48 wells.

    As of June, the realization of oil and gas lifting was still recorded at 1.6 million barrels of oil equivalent per day (BOEPD) or 95.6% of the target of 1.7 million BOEPD. In detail, oil lifting reached 666.6 thousand BPD or 94.6% of the APBN target of 705 thousand BPD, and gas was 5,430 million standard cubic feet per day/MMscfd or 96.3% of the 5,638 MMscfd targets. 

Investor Daily, Page-9, Saturday, Aug 7, 2021

Thursday, August 5, 2021

SKK Migas Encourages Completion of Goods and Services Contracts

 


    The Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas) continues to oversee the transfer of management of the Rokan Block, including contracts mirroring for the procurement of goods and services. This process must be completed immediately to keep the Rokan Block's oil production from decreasing after changing operators.

    To ensure that matters related to the contract for the procurement of goods and services run smoothly, SKK Migas together with PT Chevron Pacific Indonesia (CPI) and PT Pertamina Hulu Rokan (PHR) held an online vendor day. This activity was attended by more than 550 providers of goods and services.

Blogger Agus Purnomo In SKK Migas

    Acting Deputy for Procurement Control of SKK Migas Rudi Satwiko said the activity was part of an effort to ensure contracts and supplies continued smoothly during the transfer of management of the Rokan Block from CPI to PHR. This is important considering that the Rokan Block has very promising potential and can become one of the backbones to achieve the production target of 1 million BPD in 2030.

"The smooth transfer of management requires support from various parties, including the providers of goods and services in the Rokan Block," he said.

    According to Rudi Satwiko, since its first production in 1951, the Rokan Block has contributed to development for 70 years. This block once reached its peak of glory with oil production reaching more than 700 thousand barrels per day (BPD). Even now, this oil and gas block is still a mainstay with oil production of around 160 thousand BPD.

"The Rokan Block has contributed an average of 46 percent to national oil production, although currently, its production has decreased to 24 percent of national production," said Rudi.

    Vice President Procurement & Contract of CPI Sigit Pratopo said that his party is committed to maintaining optimal operations of the Rokan Block, including the provision of goods and services by vendors. During the preparation of contract termination and transition to PHR, his party has submitted data and information to SKK Migas and PHR which includes copies of contracts and purchase orders (PO) for contracts mirroring, copies of local vendor contracts, inventory data, and warehouse management processes.

"After the transition, CPI will continue to provide support, including continuing the process of closing contracts and POs to ensure the fulfillment of the obligations of partners providing goods and services and processing invoices for contracts and POs under the CPI entity," said Sigit.

    PHR's Business Support Project Leader Danang Ruslan Saleh explained that contracts mirroring will ensure the sustainability of contracts that have been signed when vendors become CPI partners. From a total of 379 active contracts, his party determined 318 contracts according to PHR needs and continued with the contracts mirroring process. Currently, his party has completed mirroring for 298 contracts with 4 contracts in the amendment process.

"The amendment to the contract for the provision of drilling is related to the number of drilling activities that will be added by PHR after the transfer of management so that it requires more rigs than the number in the existing contract," he said.

    Head of the Division of Supply Chain Management and Cost Analysis of SKK Migas Erwin Suryadi said, to ensure that the issue of the procurement contract for goods and services was immediately resolved, his party revised the Work Procedure Guidelines number 007 James Bond, (PTK 007) by including contract mirroring terminology. 

    This step is to maintain the continuity of the supply of goods and services so that PHR can prepare everything, including the supporting infrastructure. Thus, oil production in the Rokan Block will not decrease.

the Rokan Block by Chevron

“Contract mirroring for 1 year is not part of the project. As of August 17, 2021, PHR will have joined the centralized integrated vendor database (CIVD) to make it easier for vendors and PHR to provide goods and services in accordance with existing regulations," said Erwin.

Engaging Region

    Danang added that PHR will continue the Local Business Development (LBD) activities that have been initiated by CPI. In addition to the contract, currently PHR has prepared a work order for the next month so that after the transfer of management there will be no problems in providing goods and services to support the operations of the Rokan block.

"We are finalizing the list of owner contracts required by providers of goods and services when PHR has officially operated the Rokan block," said Danang.

    SKK Migas encourages this Local Business Development (LBD) program. The reason is, this program has a positive impact on local entrepreneurs. As of May 2021, for 11 years, LBD contracts reached Rp 1.27 trillion for 5,055 contracts requiring 40,400 workers. Therefore, his party asked PHR to increase the number of parties involved in various regions in Riau which currently consists of 14 rings in 1 area with 699 active LBD.

"Hopefully the number of LBD can be increased so that the benefits for the people of Riau will be greater," said Erwin.

    The management of the Rokan Block will switch from CPI to PHR on 9 August. As one of the mainstay oil and gas blocks, SKK Migas projects that the Rokan Block's oil production will increase to 175-180 thousand BPD in 2022. As of June, the realization of Rokan Block's production was recorded at 160,646 BPD or 97.4% compared to the lifting target in this year's APBN 165 thousand BPD.

Investor Daily, Page- 10, Thursday, Aug 5, 2021

Pertamina Prepares to Manage Rokan Block

 


    Pertamina is ready to take over the management of the Rokan Block on August 9. President Director of PT Pertamina Hulu Rokan (PHR) Jaffee A Suardin met with Riau Governor Syamsuar to convey his readiness for the transfer of management.

    Jaffee said PHR is ready to enter and manage the Rokan Block. A number of transitional preparations have been made, including those related to PT Chevron Pacific Indonesia (CPI) workers who are employees of PT PHR. A total of 2,691 CPI workers agreed to join PHR. So, later the Rokan Block operation will be carried out by the team, it will take a long time.

"Then for the work contract, we have also done mirroring with CPI and it has reached 100 percent," said Jaffee.

    Jaffee also conveyed the plan for a ceremony to transfer the management of the Rokan Block from CPI to PHR on the turn of August 8 to 9, 2021. The activity was carried out online by inviting the Riau Province Regional Leadership Communication Forum and 7 regional heads of the Rokan Block working area.

Blogger Agus Purnomo in SKK Migas

"Preparations for the ceremony have been carried out by SKK Migas, CPI, and PHR, and also ensure that the transfer of management process will run smoothly and all work in the Rokan Block can run smoothly," said Jaffee.

    Riau Governor Syamsuar appreciated the presence of the Director of PHR. He hopes that the process of managing the Rokan Block from CPI to PHR can run smoothly.

The Rokan Block by Chevron

"We hope that this transfer of management will run smoothly, work in the Rokan Block will continue and production will also continue to increase," said Syamsuar.

    He also hopes that the presence of PHR in the Rokan Block can have a good impact on the people of Riau. In this regard, the regional government has prepared Regional Selected Business Entities (BUMD) to participate in the management of this participating interest. Of course, we hope that it will have a good impact on development in Riau and the welfare of the people of Riau," said Syamsuar.

    The Rokan Block with an area of ​​6,453 km2 produces around 165,000 barrels of oil per day (BPD) or 24 percent of national oil production. To increase production after the transfer of management, PHR targets to drill 181 new wells for the period August-December 2021.

    Managing Director of Chevron Indo Asia Business Unit & President Director of Chevron Pacific, Albert Simanjuntak, said the Rokan work area is a strategic asset for state and regional revenues, the community's economy, and national energy security.

“It is an honor for us to be able to manage this asset well,” said Albert.

    He thanked the dedication and performance of tens of thousands of Chevron employees, including retirees over the years.

    According to him, the strong performance of Rokan's work area so far is inseparable from the Human Resources factor behind it, namely employees with existing skills, culture, and work ethic. He is optimistic that they can make a big contribution to the new company.

Republika, Page- 9, Thursday, Aug 5, 2021

Production Targeted to Increase

 


    After officially managing the Rokan Block, PT Pertamina (Persero) through PT Pertamina Hulu Rokan (PHR) is targeted to be able to produce oil with higher achievements.


    Deputy for Operations of the Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas) Julius Wiratno said that with the number of drilling activities and the availability of more massive tools, production in the Rokan Block is targeted to increase.

"Until December 2021, with around 17-18 rigs drilling, production could be around 175,000-180,000 barrels per day," he said.

Blogger Agus Purnomo in SKK Migas

    Meanwhile, based on SKK Migas data, production in the Rokan Block throughout the first semester of 2021 by PT Chevron Pacific Indonesia (CPI) was at the level of 160,646 barrels of oil per day (BPD), this figure is lower than the target set in the 2021 State Budget of as much as 165,000 BPD.


    President Director of PT Pertamina Hulu Rokan (PHR) Jaffee Suardin believes production in the Rokan Block can increase when the transfer of management is carried out. The reason is, throughout this year Pertamina is targeting massive drilling. PT Chevron Pacific Indonesia (CPI) plans to drill as many as 161 wells after the transfer of management in the Rokan Block which will begin on August 9, 2021.

The Rokan Block by Chevron

    Jaffee said that there will be an additional 77 wells from CPI's commitment which will not be completed until the management transfer period on August 9th. In the previous target, Pertamina planned to drill only 84 wells for 2021.

"As of December 161 wells, the target production level is maintained and can increase," he said.

    Jaffee said PT Pertamina Hulu Rokan (PHR) had prepared the resources needed to realize the plan. To realize the Wells drilling plan, 16 to 17 rigs have been prepared.

    In addition, Jaffee said that all human resources, as well as supporting materials, have been prepared so that when the transition period is over, all activities can start immediately.

"For that, we continue to make preparations, from Pertamina's side, the planned number of rigs, materials, from Pertamina's side, are ready. So, the goal is that the transfer of management process will run smoothly without any disturbances,” said Jaffee.

Bisnis Indonesia, Page- 4, Thursday, Aug 5, 2021

Wednesday, August 4, 2021

Pertamina Continues 318 Contracts for Goods and Services in the Rokan Block

    PT Pertamina Hulu Rokan (PHR) will continue with 318 contracts for the supply of goods/services with vendors who previously partnered with PT Chevron Pacific Indonesia (CPI). This step is considered to guarantee the continuity of the procurement of goods/services after the transfer of management of the Rokan Block, Riau, from Chevron to Pertamina starting August 9, 2021.

    Regarding the partnership, the Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas) hopes that PT Pertamina Hulu Rokan (PHR) will increase the empowerment of local vendors. PHR Business Support Project Leader Danang Ruslan Saleh assessed that 318 contracts out of 379 active contracts were in accordance with the company's needs.

"A total of 298 contracts have been completed in the mirroring process to ensure the continuation of the contracts that were signed when the vendor became a partner of Chevron Pacific Indonesia," he said.

    A total of four contracts of which are in the process of being amended due to the addition of post-management drilling activities. As a result, the need for rigs will be more than the rigs in the current contract. Not only contracts, but PHR has also prepared a work order for the next month so that there are no problems in providing goods/services in the operation of the Rokan Block after the management transfer.

Blogger Agus Purnomo in SKK Migas

    In addition, PHR will continue the local business development activities initiated by Chevron. Chevron Pacific Indonesia VP Procurement & Contract Sigit Pratopo said his party had provided data and information to SKK Migas and PHR, including a copy of the contract and purchase request for the mirroring process, a copy of the local business development/LBD contract for the procurement process, as well as inventory data for warehouse management by PHR.

the Rokan Block by Chevron

    This step is one way to keep the operation of the Rokan Block optimal. Post-transition, Chevron will continue the process of contract closing and purchase requests. The goal is to ensure the fulfillment of the obligations of partners providing goods/services as well as paying contract bills and purchase requests under the Chevron Pacific Indonesia entity.

    Regarding contracts with local businesses, the Head of the Division of Supply Chain Management and Cost Analysis of SKK Migas Erwin Suryadi said PHR could increase the number of LBDs involved in Riau. Currently, Riau consists of 14 areas of ring one with a total of 699 active LBD actors.

    SKK Migas data as of May 2021 shows that the contract for the procurement of goods/services with LBD for 11 years reaches Rp 1.27 trillion and requires 40,400 workers. That value is equivalent to 5,055 contracts. He added, as of August 17, 2021, PHR will be included in the centrally integrated vendor database (CVID).

    Thus, PHR and the vendors involved can more easily provide goods/services according to existing regulations. In addition, a one-year mirroring contract is considered important to maintain the continuity of the supply of goods/services until PHR can prepare the needs, including supporting infrastructure. According to the Executive Director of the Reforminer Institute, Komaidi Notonegoro, increasing the involvement of local vendors requires careful and structured planning.

“Procurement of goods/services in upstream oil and gas requires high technology. Currently, goods/services with the same specifications, local players tend to be more expensive,” he said.

    Acting Deputy for Procurement Control of SKK Migas, Rudi Satwiko, stated that contracts and supplies need to be ensured that they are smooth during the transfer of management. Rokan Block production currently contributes 24 percent to national performance. 

    However, the average production has contributed 46 percent. He is optimistic that the potential of this block is still promising and can be one of the pillars to achieve oil production of 1 million barrels per day in 2030.

Kompas, Page-11, Wednesday, August 4, 2021

Saturday, July 31, 2021

Chevron Completes 100 Wells, Pertamina Continues to Drill 130 Wells

    PT Pertamina Hulu Energi (PHE) through its subsidiary, PT Pertamina Hulu Rokan (PHR), will drill 130 wells in the Rokan Block this year, continuing drilling by PT Chevron Pacific Indonesia (CPI) which has reached 100 wells. Wells, drilling is needed to maintain the level of oil production in this oil and gas block.

the Rokan Block Chevron

    PHE Development and Production Director Taufik Adityawarman said optimizing the production of the Rokan Block is one of the strategies to achieve the company's oil and gas production target this year. For this reason, once the management shifts to Pertamina on August 9, it will increase the drilling of wells in this block.

PHR plans to drill approximately 130 development wells in 2021 which includes the remaining wells from PT CPIPHR is also preparing approximately 290 wells in 2022. This is the oil and gas block with the highest number of Wells investments," he said at the Upstream Subholding Media Gathering.

    To support the Wells drilling target, the company will also add 10 drilling rigs. So, there will be a total of 16 drilling rigs and 29 rigs for workover and well services operating in the Rokan Block. The procurement of this rig is a mirroring of the previous contract.

    Meanwhile, in its official statement, PT CPI as the existing operator stated that it has completed drilling 100 wells, including 11 conversion wells, in the Rokan Block since the end of December 2020. CPI has also succeeded in adding rigs so that now there are 8 drilling rigs actively operating in the field.

“The Rokan Block is an important strategic asset for state and regional revenues, the community's economy, and national energy security. The collaboration between SKK Migas, PT CPI, and PT Pertamina Hulu Rokan (PHR) is going well so that the drilling program can take place safely and smoothly," said the Director of Rokan PT CPI Budianto Renyut.

Blogger Agus Purnomo SKK Migas

    The Head of Representative for the Special Task Force for Upstream Oil and Gas (SKK Migas) Northern Sumatra Rikky Rahmat Firdaus revealed that his party is committed to assisting, facilitating, and coordinating with stakeholders in the region to complete preparations for the drilling implementation so that it can be carried out smoothly and efficiently. safe.

"It takes full support from all stakeholders from the center to the regions so that the target to maintain and maintain production in the Rokan Block can be achieved. This method will increase state revenue,” said Rikky.

    To ensure the availability of supplies of materials to support the drilling program, PT CPI and PHR have signed a joint utilization agreement of state-owned warehouse facilities in the Rokan Block on April 21. Thus, PHR can begin to import and store materials to support the drilling program in warehouses managed by PT CPI in Duri and Dumai.

    These materials include pipes, conductors, casings, tubing, wellheads, valves, cables, and bobbing pumps. Currently, a number of PHR materials have arrived at PT CPI's warehouse.

"Hopefully, after the date of the transfer of management later, the drilling program can continue without any disruption to material supply because PHR's materials are already available in the field," said Budianto.

Investor Daily, Page-9-Saturday, July 31, 2021

Thursday, July 29, 2021

Accelerating EOR Implementation, Oil and Gas Companies are Encouraged to Partner

    Minister of Energy and Mineral Resources (ESDM) Arifin Tasrif encourages oil and gas companies to cooperate with other parties to realize advanced oil recovery (EOR) activities. The implementation of this activity is one way to achieve the oil production target of 1 million barrels per day (BPD) in 2030.

    Arifin said that accelerating the implementation of advanced production, both secondary and tertiary recovery, needs to be done to achieve the oil production target of 1 million bpd and gas 12 Billion Standard Cubic Feet Per Day/BSCFD by 2030. This acceleration is expected to provide additional contributions to national oil production. For this reason, cooperation contract contractors (KKKS) are encouraged to partner with other parties so that the EOR project can be started immediately.

“To realize the goals in 2030, several EOR projects must be planned and carried out immediately. The government also encourages KKKS to establish strategic cooperation with other parties who have competence and experience in the development and implementation of EOR," said Arifin.

Blogger Agus Purnomo in SKK Migas

    Head of the Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas) Dwi Soetjipto said that there were 23 EOR projects scheduled to operate in stages until 2030. Regarding the progress of the EOR implementation, 23 fields are still in the study stage. Meanwhile, one field is working on a field trial and one field is in the process of discussing a development plan (POD).

    Of the 23 EOR projects, most of them are Pertamina Group projects. In detail, PT Pertamina Hulu Rokan will run 7 EOR projects, PT Pertamina EP 2 projects, PT Pertamina Ogan Komering 2 projects, PT Pertamina Hulu Energi North West Java (ONWJ) 2 projects, PT Pertamina Hulu Offshore South East Sumatra (OSES) 2 projects, PT Pertamina Hulu Energi Siak 1 project, PT Pertamina Hulu Mahakam 1 project, and PT Pertamina Hulu Energi Tuban 1 project.

    In addition, BOB Bumi Siak Pusako will work on 1 EOR project, PT Energi Mega Persada (EMP) 1 project, Medco E&P Indonesia 1 project, and Petrogas 1 project. Referring to SKK Migas data, the full scale implementation schedule for these EOR projects is Minas and Batang in 2024, Bekasap and E-main in 2025, Zulu in 2026, Tanjung, Rama, and Handil in 2027, Pedada, Sukowati, Gemah, Melibur, and Walio in 2028, Duri Ring, Bekasap, Kulin, Balam South, Bangko, and Kaji Hopefully in 2029, and Air Serdang, Guruh, Krisna, and Mudi in 2030.

    Previously, SKK Migas Deputy Operations Julius Wiratno said that his party together with Pertamina were finalizing the POD of EOR implementation in the Rokan Block. One of them is the implementation of surfactant EOR in Minas Field, Rokan Block. The POD is targeted to be approved this year as well. If successful, this step is expected to contribute to the production of the Rokan Block in 2023-2024.

Transfer Manage

    Arifin also revealed the importance of proper and effective management transfer of terminated oil and gas blocks in maintaining national oil and gas production this year, which will also have an impact on the 2030 target. For this reason, Arifin reminded SKK Migas to continue to oversee the transfer of management of the Rokan Block from PT Chevron Pacific Indonesia ( CPI) to PT Pertamina Hulu Rokan (PHR) on 8 August.


"To maintain the level of national oil and gas production, I have a special message that the transfer of management of the Rokan Block is properly guarded so that the transfer of management process can take place smoothly without disturbing the level of oil production in this block," said Arifin.

    He admitted that this year was very challenging for the upstream oil and gas industry. The realization of oil lifting to date is still at 666.6 thousand BPD and gas at 5,430 million standard cubic feet per day/MMscfd. Meanwhile, the target of the State Revenue and Expenditure Budget is 705 thousand BPD for oil lifting and 5,638 MMScfd for gas.

"2021 will be a year of proving the resilience of the upstream oil and gas industry to maintain production," he said.

    Julius had said that his party was optimistic that oil production in the Rokan Block could rise again despite the transfer of management. The reason is, even now, there are indications of an increase in production by carrying out massive Wells drilling during the operatorship transition period. Next year, the production of this block is expected to return to the level of 175-180 thousand BPD.

    The implementation of Wells drilling is one of the nine issues monitored by SKK Migas in the transfer of management of the Rokan Block. Until now, the realization of drilling development wells in the Rokan Block has reached 83 wells from the target of 180 wells this year. Furthermore, the realization of rework (workover) wells as many as 40 wells from the target of 39 wells, and well services (well services) 5,135 activities out of a target of 6,819 activities.

Investor Daily, Page-10, Thursday, July 29, 2021