Friday, November 2, 2018

Extension of Masela Block Contract Agreed



The government agreed to Inpex Corporation's request that the Abadi Plant, Masela Block contract be extended for 20 years. The Director General of Oil and Gas, Ministry of Energy and Mineral Resources Djoko Siswanto said that in principle, the ESDM Ministry agreed to extend the Masela contract even though Inpex had not submitted administrative requirements.

The Masela Block

The Masela Block contract will expire on November 28, 2028. Based on the applicable regulations, the contract extension can be submitted no later than 10 years before the contract expires. This means that Inpex can apply for a Masela contract extension starting November 28, 2018.

"Later November 28 [2028] the Masela Block contract ends. So, in November 2018, Inpex can apply to extend the contract. Already there is talk, later on the administration on November 28, in principle we are okay, "he said.


Inpex immediately submitted a revision of the Masela Block plan of development (PoD) after the Japanese oil and gas company completed a pre-FEED preliminary technical design study. Inpex revised POD after President Joko Widodo requested that the floating LNG refinery be replaced with a land refinery.

"This year is the agreement [PoD]. The government asks Inpex to quickly submit PoD. Next month."

Meanwhile, Inpex has not yet determined the location of the Abadi Masela LNG refinery. Inpex Corporation's Senior Media Relations Specialist Moch. Nunung Kurniawan said that currently his party is consulting with the government regarding the location of the LNG plant.

On the other hand, SKK Migas is still awaiting the readiness of gas buyers from the provocation of the SWB / WB / SB oil and gas production facilities worked on by PetroChina Intl. Jabung Ltd.


SKK Migas Program and Communication Division Head Wisnu Prabawa Taher said the construction of the oil and gas production facility project had begun. However, PetroChina is still awaiting gas buyers' readiness.

"Only later when the buyer's facilities are ready will the gas be sent."

The province will produce 12 MMscfd of gas and a production facility capacity of 14.5 MMscfd. Wisnu said, the project is targeted to start operating in the first quarter of 2019. The SWB / WB / SB upstream oil and gas project worked on by PetroChina Intl. Jabung Ltd is one of 13 upstream oil and gas projects targeted to operate in 2019.

IN INDONESIA

Perpanjangan Kontrak Blok Masela Disepakati


Pemerintah menyetujui permintaan lnpex Corporation agar kontrak Lapangan Abadi, Blok Masela diperpanjang selama 20 tahun. Direktur Jenderal Minyak dan Gas Bumi, Kementerian Energi dan Sumber Daya Mineral Djoko Siswanto mengatakan bahwa pada prinsipnya, Kementerian ESDM sepakat untuk memperpanjang kontrak Masela meskipun Inpex belum mengajukan persyaratan administrasi.

Kontrak Blok Masela akan berakhir pada 28 November 2028. Berdasarkan regulasi yang berlaku, perpanjangan kontrak bisa diajukan paling cepat 10 tahun sebelum kontrak berakhir. Artinya, Inpex dapat mengajukan perpanjangan kontrak Masela mulai 28 November 2018.

“Nanti 28 November [2028] berakhir kontrak Blok Masela. Jadi, pada November 2018, Inpex dapat mengajukan perpanjang kontrak. Sudah ada pembicaraan, nanti administrasinya 28 November prinsipnya kami sudah oke,” katanya.

Inpex segera mengajukan revisi rencana pengembangan (plan of development/PoD) Blok Masela setelah perusahaan migas dari Jepang itu menyelesaikan kajian awal desain teknis konstruksi (pre-FEED). Inpex merevisi POD setelah Presiden Joko Widodo meminta kilang LNG terapung diganti dengan kilang darat.

“Tahun inilah persetujuannya [PoD]. Pemerintah minta Inpex biar cepat mengajukan PoD. Bulan depan.”

Sementara itu, Inpex belum menentukan lokasi kilang LNG Abadi Masela. Senior Specialist Media Relations Inpex Corporation Moch. Nunung Kurniawan mengatakan bahwa saat ini pihaknya berkonsultasi dengan pemerintah perihal lokasi kilang LNG. 

Di sisi lain, SKK Migas masih menunggu kesiapan pembeli gas dari provek fasilitas produksi migas SWB/ WB/SB yang digarap oleh PetroChina Intl. Jabung Ltd. 

Kepala Divisi Program dan Komunikasi SKK Migas Wisnu Prabawa Taher mengatakan, konstruksi proyek fasilitas produksi migas tersebut sudah dimulai. Namun, PetroChina masih menunggu kesiapan pembeli gas. 

“Baru nanti kalau fasilitas pembeli sudah siap akan dikirim gasnya.”

Provek tersebut akan menghasilkan gas 12 MMscfd dan kapasitas fasilitas produksi sebanyak 14,5 MMscfd. Wisnu menuturkan, proyek tersebut ditargetkan mulai beroperasi pada kuartal I/2019. Proyek hulu migas SWB/WB/SB yang digarap oleh PetroChina Intl. Jabung Ltd ini merupakan salah satu dari 13 proyek hulu migas yang ditargetkan beroperasi pada 2019.

Bisnis Indonesia, Page-24, Wednesday, Oct 31, 2018

Monday, October 29, 2018

ConocoPhillips Submits Corridor Block Proposal



The Ministry of Energy and Mineral Resources (ESDM) said that Conoco-Philips had submitted a proposal to develop the Corridor Block after its contract expired in 2023. Conoco-Philips is the existing block contractor.



ESDM Ministry's Director General of Oil and Gas, Djoko Siswanto, said that the development proposal had been submitted. The proposal is a complete document of the planned development of the Corridor Block from technical and commercial aspects.

"This (proposal) is being discussed. We have received the proposal, "he said in Jakarta.

Djoko had explained, currently the Corridor Block participating rights holders are Philip Conoco 54%, PT Pertamina Hulu Energi Corridor 10%, and Repsol 36%. Conoco Philip said that he would still cooperate with Repsol in working on the Corridor Block after the production sharing contract (PSC) was completed in 2023. While Pertamina proposed 100% participation rights after 2023.

"Pertamina has submitted its proposal, very thick. So it takes time (for evaluation), "Djoko said.

Vice President of Commercial, Business Development & Relations, ConocoPhillips Indonesia, Taufik Ahmad confirmed that his party had submitted a proposal to extend the management of the Corridor Block to the government.

"I can confirm that we have submitted a proposal to extend the Corridor Block on September 27," he said

The Corridor Block is one of three oil and gas blocks that will expire in 2023 in cooperation contracts. Referring to the ESDM Ministry's initial plan, the fate of the block that expires its 2023 contract will be decided this October. Therefore, the government had previously given ConocoPhillips time until the end of September to submit its proposal.

Until last July, the realization of gas production from the Corridor Block was recorded at 828.41 million standard cubic feet per day / mmscfd, exceeding the target of 810 mmscfd. But until the end of the year, the production of this block is projected to be only 800 mmscfd. While next year, the Corridor Block is targeted to produce 810 mmscfd of gas. The Corridor Block contract was signed in 1983 and ends on December 19, 2023.

According to information on the ConocoPhilip page, the Corridor Block consists of two oil producing fields and seven gas fields. This oil field is Suban Baru and Rawa, while the gas fields are Suban, Sumpal and Dayung. Gas produced from the Corridor Block is sold through long-term contracts into the country and Singapore.

Currently ConocoPhilip continues to invest in maintaining the Corridor Block gas production. Conoco Philips drills development wells in Sumpal and Suban. In addition, the US oil and gas company built additional compressor facilities in Suban.



While the other two oil and gas blocks that were completed in 2023 are Rimau and Jabung blocks, currently managed by Petrochina International Jabung Ltd with participating rights (participating interest / PI) 42.86%, while other PI holders are Petronas Carigali 42.86 % and PT Pertamina (Persero) 14.29%. 



   Until last July, the block's oil production was recorded at 14,525 barrels per day (hph) and gas 210.1 mmscfd. This block contract expires on February 26, 2023.

IN INDONESIAN

ConocoPhillips Serahkan Proposal Blok Koridor


Kementerian Energi dan Sumber Daya Mineral (ESDM) menyatakan Conoco-Philips telah memasukkan proposal rencana pengembangan Blok Koridor pasca kontraknya berakhir pada 2023. Conoco-Philips merupakan kontraktor eksisting blok ini.

Direktur Jenderal Minyak dan Gas Bumi Kementerian ESDM Djoko Siswanto mengatakan, proposal pengembangan itu telah diserahkan. Proposal merupakan dokumen lengkap rencana pengembangan Blok Koridor dari aspek teknis dan komersil. 

“Ini (proposal) sedang dibahas. Kami sudah terima proposalnya,” kata dia di Jakarta.

Djoko sempat menjelaskan, saat ini pemegang hak partisipasi Blok Koridor adalah Conoco Philip 54%, PT Pertamina Hulu Energi Corridor 10%, dan Repsol 36%. Conoco Philip dikatakannya masih akan menggandeng Repsol dalam menggarap Blok Koridor setelah kontrak kerja sama (production sharing contract/ PSC) selesai di 2023. Sementara Pertamina mengajukan kepemilikan hak partisipasi 100% setelah 2023.

“Pertamina sudah memasukkan proposalnya, sangat tebal. Jadi perlu waktu (untuk evaluasi),” tutur Djoko.

Vice President Commercial, Business Development & Relations ConocoPhillips Indonesia Taufik Ahmad membenarkan bahwa pihaknya sudah memasukkan proposal perpanjangan pengelolaan Blok Koridor ke pemerintah. 

“Saya bisa mengkonfirmasi bahwa kami sudah memasukkan pengajuan perpanjangan Corridor Block pada 27 September,” tuturnya 

Blok Koridor merupakan satu dari tiga blok migas yang akan berakhir kontrak kerja samanya pada 2023. Mengacu rencana awal Kementerian ESDM, nasib blok yang habis kontraknya 2023 akan diputuskan pada Oktober ini. Karenanya, pemerintah sebelumnya memberikan waktu kepada ConocoPhilips sampai akhir September untuk menyerahkan proposalnya. 

Hingga Juli lalu, realisasi produksi gas dari Blok Koridor tercatat sebesar 828,41 million standard cubic feet per day/mmscfd, melebihi target 810 mmscfd. Namun sampai akhir tahun nanti, produksi blok ini diproyeksikan hanya 800 mmscfd. Sementara pada tahun depan, Blok Koridor ditargetkan menghasilkan gas 810 mmscfd. Kontrak Blok Koridor ditandatangani pada 1983 dan berakhir pada 19 Desember 2023.

Menurut keterangan dalam laman ConocoPhilip, Blok Koridor terdiri dari dua lapangan penghasil minyak dan tujuh lapangan gas. Lapangan minyak ini yakni Suban Baru dan Rawa, sementara lapangan gasnya adalah Suban, Sumpal, dan Dayung. Gas yang dihasilkan dari Blok Koridor dijual melalui kontrak jangka panjang ke dalam negeri dan Singapura.

Saat ini ConocoPhilip terus berinvestasi guna menjaga produksi gas Blok Koridor. Conoco Philips melakukan pengeboran sumur pengembangan di Sumpal dan Suban. Selain itu, perusahaan migas Amerika Serikat itu membangun fasilitas kompresor tambahan di Suban.

Sementara dua blok migas lain yang selesai kontraknya pada 2023 yakni Blok Rimau dan Jabung, saat ini dikelola oleh Petrochina International Jabung Ltd dengan kepemilikan hak partisipasi (participating interest/ PI) 42,86%, sementara pemegang PI yang lain adalah Petronas Carigali 42,86% dan PT Pertamina (Persero) 14,29%. Sampai Juli lalu, produksi minyak blok ini tercatat sebesar 14.525 barel per hari (hph) dan gas 210,1 mmscfd. Kontrak blok ini habis pada 26 Februari 2023. 

Investor Daily, Page-9, Wednesday, Oct 3, 2018

Thursday, October 11, 2018

Gas Supply Still Surplus Until 2024



Based on the 2018-2027 Indonesia Natural Gas Balance Sheet, gas supply up to 2024 is still surplus, so there is no need for imports. However, the gas balance has a potential deficit from 2025. The gas balance does not take into account production and the Abadi Field, Masela Block and East Natuna Block. Both oil and gas working areas have very significant gas reserves. When calculating gas production from the two jumbo fields, gas supply in the country is still quite abundant.

Indonesian Gas Balance 2018-2027 issued by the Ministry of Energy and can help investors, business entities, and ministries / institutions that want data and information related to national natural gas. The composition of domestic natural gas utilization in 2017 rose to 59%, while exports were 41%. Domestic natural gas utilization consists of industry (23.18%), electricity (14.09%), fertilizer (10.64%), oil and gas lifting (2.73%), and domestic liquefied natural gas / LNG (5, 64%).

In addition, domestic gas is also used for domestic LPG / LPG (2.17%) and household gas networks and gas refueling stations (0.15%). Exports of natural gas amounting to 41% consist of shipping through pipes 12.04% and in the form of LNG amounting to 29.37%. ESDM Deputy Minister Arcandra Tahar said that the preparation of the gas balance resulted in three natural gas consumption and supply scenarios.

The method for preparing the Indonesian Gas Balance Sheet 20-20-2027 has differences with the Indonesia Gas Balance 2009-2017. Based on the previous gas balance, gas demand comes from the need for contracted gas and potential gas needs.

"So today is clarification if there are some doubts [related to our gas balance. For each region, don't misperceive. There are some regions say shortage [gas deficit], this is an assumption now not in the next few years, "he said in the presentation of the Indonesian Gas Balance Sheet 2018-2027.

In the 2009-2017 Indonesia Gas Balance, the growth dynamics of natural gas demand shows fluctuating data. For example, the growth of gas demand in 2010 was 8%, while in 2015 only 5%. Arcandra said that the fluctuations in the growth of gas demand were due to unstable policies and the average price of different gases.

"However, this is not connected to ICP [Indonesian crude oil], the price of the pipeline gas continues to rise. But the key price of gas is upstream and midstream [distribution], "he added.

Meanwhile, the projection of gas needs in the Indonesia Gas Balance 2018-2027 is divided into three scenarios. Scenario I, the gas balance in 2018-2027 is surplus. The surplus gas balance because the gas demand projection calculation refers to the realization of natural gas utilization and the long-term pipeline and LNG gas export contracts are not extended.

The balance sheet uses the projected growth of the gas industry to grow 1.1% and Indonesia's economic growth of 5.5%. Scenario II, the gas balance in 2018-2024 remains surplus. However, the gas balance in 2025-2027 has a potential natural gas deficit. The calculation has not considered the potential gas supply from the discovery of new reserves and future gas contracts such as the Masela Block and East Natuna Block.

East Natuna Block

In the scenario of the Ministry of Energy and Mineral Resources, the assumption of using gas from existing contracts is 100% realized. The use of gas for the electricity sector is also projected in accordance with the 2018-2027 General Electricity Procurement Plan (RUPTL). The assumption of growth in natural gas demand is in line with economic growth, which is 5.5% for the retail industry sector. In addition, the implementation of the revitalization of the oil refinery operates in accordance with the target. The construction of a petrochemical and fertilizer plant is also assumed to operate on schedule.

Scenario III, the gas balance is projected to be surplus in the period 2019-2024. Meanwhile, in 2025-2027 there is a potential natural gas deficit. However, in scenario III, the Ministry of Energy and Mineral Resources has not considered the potential of gas supply from the discovery of new reserves and future gas contracts such as the Masela Block and East Natuna Block.

The projection of gas requirements in scenario III uses the assumption that gas utilization from existing contracts is 100% realized and gas utilization for the electricity sector is in accordance with RUPTL 2018-2027. In addition, the retail industry sector utilizes gas at maximum plant capacity and increases demand from economic growth of 5.5%.

In addition, the implementation of the revitalization of the oil refinery is projected on schedule. Implementation of the construction of a new petrochemical and fertilizer plant on schedule. Arcandra said that with different methodologies, Indonesia's natural gas balance would be recalculated every year. It follows the revised RUPTL which is also revised every year.

"Why change because the biggest off taker is PT. PLN and they also changed [RUPTL]. "

SLOW INFRASTRUCTURE

On the other hand, businesses complain that the development of natural gas infrastructure is operating slowly so that the industry still faces challenges in the price and supply of natural gas. In the 2018-2027 Indonesia Natural Gas Balance Sheet, domestic gas needs until 2024 are still in surplus. However, gas supply from 2025 must be added. Additional gas supply can be done through increasing new gas reserves and accelerating the development of potential gas fields.

Chairman of the Glass and Sheet Glass Association Yustinus H. Gunawan said, from the exposure to the gas balance, the government actually provided an opportunity to reduce gas prices. However, the government only looks at the economic and gas infrastructure factors. In fact, infrastructure development such as gas pipelines can spur industrial growth. The Cirebon-Semarang segment gas pipeline plan can supply gas to industries around the pipeline.

"Floating storage regasification units [gas storage and regasification facilities] also cannot be handled. In fact, the key to the gas is infrastructure because the gas must be flowed continuously. And what is most likely to continue to be used is the pipe, "he said.

According to him, interconnection region 1 (northern Sumatra) -region 3 (Central Java) is most likely to occur with pipeline infrastructure. He cited the connection between the Cirebon-Semarang gas pipeline, not only providing solutions to industrial players in Central Java, but also connecting Sumatra and Java gas connections. Block A gas production in Aceh of 67.4 MMscfd will also increase gas supply in region 1.



Gas supply in the region I (northern Sumatra) can increase from PHE NSO-NSB and ENI Krueng Mane Ltd. Gas supply in region 2 (central, southern and West Java Sumatra) faces the challenge of reducing Pertamina EP Asset II gas production. Lampung FSRU facilities can be an alternative to supply gas in the region. However, the price of gas from the FSRU is still an obstacle because it is still considered too high. There are several strategic upstream oil and gas projects in the region 2, such as Bison, Iguana, Gajah Puteri and field development by Premier Oil with an estimated gas production of 163 MMscfd in the 3/2019 quarter.



In addition, there is a potential supply of East Natuna gas supply of 1,000 MMscfd and PetroChina for Tiung Field in central and southern Sumatra reaching 100 MMscfd in 2027. Region 3 (East Java) can rely on the Semarang-Gresik gas pipeline with gas supply from Jambaran Field -Tiimg Biru. President Director & CEO of PT Bakrie & Brothers Tbk. Bobby Gafur Umar said that the development of gas pipelines must look at the economic aspects, namely from the supply and demand side.

"If we look at the supply, there is a lot of surplus, but if there is no demand, that is what is now being identified in East Kalimantan and South Kalimantan [Bakrie gas pipeline project," he said.

According to him, the concept of gas pipeline development is not much different from toll roads, namely the potential of customers and users of these facilities.

"Deputy Minister Arcandra Tahar said that gas supply would not occur if there was no infrastructure. Well, we are now ready with supply, until the end of the year it is expected that gas demand from consumers will be known.

IN INDONESIA

Suplai Gas Masih Surplus Sampai 2024


Berdasarkan Neraca Gas Bumi Indonesia 2018-2027, pasokan gas hingga 2024 masih surplus sehingga tidak perlu impor. Namun, neraca gas berpotensi defisit mulai 2025. Neraca gas tersebut belum memperhitungkan produksi dan Lapangan Abadi, Blok Masela dan Blok East Natuna. Kedua wilayah kerja migas itu memiliki cadangan gas sangat signifikan. Bila memperhitungkan produksi gas dari kedua lapangan jumbo tersebut, pasokan gas di Tanah Air masih cukup melimpah.

Neraca Gas Indonesia 2018-2027 yang diterbitkan Kementerian Energi dan dapat membantu investor, badan usaha, dan kementerian/lembaga yang menginginkan data dan informasi terkait gas bumi nasional. Komposisi pemanfaatan gas bumi di dalam negeri pada 2017 naik menjadi 59%,sedangkan ekspor 41%. Pemanfaatan gas bumi domestik tersebut terdiri atas industri (23,18%), kelistrikan (14,09%), pupuk (10,64%), lifting migas (2,73%), dan liquefied natural gas/ LNG domestik (5,64%).

Selain itu, gas domestik juga digunakan untuk elpiji/LPG domestik (2,17%) dan jaringan gas rumah tangga dan stasiun pengisian bahan bakar gas (0,15%). Ekspor gas bumi sebesar 41% terdiri atas pengiriman melalui pipa 12,04% dan dalam bentuk LNG sebesar 29,37%. Wakil Menteri ESDM Arcandra Tahar mengatakan bahwa penyusunan neraca gas itu menghasilkan tiga skenario konsumsi dan pasokan gas bumi.

Metode penyusunan Neraca Gas Indonesia 20l8-2027 memiliki perbedadan dengan Neraca Gas Indonesia 2009-2017. Berdasarkan neraca gas sebelumnya, kebutuhan gas berasal dari kebutuhan gas yang sudah terkontrak dan kebutuhan gas yang masih potensial.

“Jadi hari ini klarifikasi kalau ada beberapa keraguan [terkait dengan neraca gas kita. Bagi per region juga, jangan salah persepsi. Ada region katakan shortage [defisit gas] sekian, ini asumsi sekarang bukan beberapa tahun mendatang,” katanya dalam paparan Neraca Gas Bumi Indonesia 2018-2027.

Dalam Neraca Gas Indonesia 2009-2017, dinamika pertumbuhan kebutuhan gas bumi menunjukkan data yang fluktuatif. Sebagai contoh, pertumbuhan kebutuhan gas pada 2010 sebesar 8%, sedangkan pada 2015 hanya 5%. Arcandra menyebut, fluktuasi pertumbuhan kebutuhan gas itu sebagai akibat kebijakan yang tidak stabil dan rerata harga gas yang berbeda.

“Namun, ini tidak tersambung ke ICP [minyak mentah Indonesi], harga gas pipa itu naik terus. Tapi kunci harga gas itu di hulu dan midstream [distribusi],” tambahnya. 

Sementara itu, proyeksi kebutuhan gas dalam Neraca Gas Indonesia 2018-2027 dibagi menjadi tiga skenario. Skenario I, neraca gas pada 2018-2027 surplus. Neraca gas surplus karena perhitungan proyeksi kebutuhan gas mengacu pada realisasi pemanfaatan gas bumi serta tidak diperpanjangnya kontrak-kontrak ekspor gas pipa dan LNG untuk jangka Panjang.

Neraca itu menggunakan proyeksi pertumbuhan industri gas tumbuh 1,1% dan pertumbuhan ekonomi Indonesia 5,5%. Skenario II, neraca gas pada 2018-2024 tetap surplus. Namun, neraca gas pada 2025-2027 ada potensi defisit gas bumi. Hitungan tersebut belum mempertimbangkan adanya potensi pasokan gas dari penemuan cadangan baru dan kontrak gas di masa mendatang seperti Blok Masela dan Blok East Natuna.

Dalam skenario Kementerian ESDM menggunakan asumsi pemanfaatan gas dari kontrak yang sudah ada terealisasi 100%. Pemanfaatan gas untuk sektor kelistrikan juga diproyeksikan sesuai dengan Rencana Umum Pengadaan Tenaga Listrik (RUPTL) 2018-2027. Asumsi pertumbuhan permintaan gas bumi sesuai dengan pertumbuhan ekonomi, yaitu 5,5% untuk sektor industri ritel. Selain itu, pelaksanaan revitalisasi kilang minyak beroperasi sesuai dengan target. Pelaksanaan pembangunan pabrik petrokimia dan pupuk juga diasumsikan beroperasi sesuai jadwal.

Skenario III, neraca gas diproyeksi surplus dalam kurun 2019-2024. Sementara itu, pada 2025-2027 terdapat potensi defisit gas bumi. Namun, dalam skenario III, Kementerian ESDM belum mempertimbangkan potensi pasokan gas dari penemuan cadangan baru dan kontrak gas di masa mendatang seperti Blok Masela dan Blok East Natuna.

Proyeksi kebutuhan gas pada skenario III menggunakan asumsi pemanfaatan gas dari kontrak yang sudah ada terealisasi 100% dan pemanfaatan gas untuk sektor kelistrikan sesuai dengan RUPTL 2018-2027. Selain itu, sektor industri ritel memanfaatkan gas pada kapasitas pabrik maksimum serta penambahan permintaan dari pertumbuhan ekonomi 5,5%. 

Selain itu, pelaksanaan revitalisasi kilang minyak diproyeksikan sesuai jadwal. Pelaksanaan pembangunan pabrik baru petrokimia dan pupuk sesuai jadwal. Arcandra mengatakan bahwa dengan adanya perbedaan metodologi, neraca gas bumi Indonesia akan dihitung ulang setiap tahun. Hal itu mengikuti perubahan RUPTL yang juga direvisi setiap tahun. 

“Kenapa berubah karena off taker [penyerap] terbesarnya itu PT. PLN dan mereka juga berubah [RUPTL].”

INFRASTRUKTUR LAMBAT

Di sisi lain, pelaku usaha mengeluhkan pembangunan infrastruktur gas bumi beroperasi lambat sehingga industri masih menghadapi tantangan harga dan suplai gas bumi. Dalam Neraca Gas Bumi Indonesia 2018-2027, kebutuhan gas domestik sampai 2024 masih surplus. Namun, pasokan gas mulai 2025 harus ditambah. Tambahan suplai gas dapat di lakukan melalui peningkatan cadangan gas baru dan percepatan pengembangan lapangan gas potensial.

Ketua Umum Asosiasi Kaca Lembaran dan Pengaman Yustinus H. Gunawan mengatakan, dari paparan neraca gas itu terlihat pemerintah sebenarnya memberikan peluang untuk menurunkan harga gas. Namun, pemerintah hanya melihat faktor keekonomian dan infrastruktur gas. Padahal, pembangunan infrasturktur seperti pipa gas mampu memacu pertumbuhan industri. Rencana pipa gas ruas Cirebon-Semarang dapat menyuplai gas untuk industri di sekitar jalur pipa tersebut.

“Floating storage regasification unit [fasilitas penyimpanan dan regasifikasi gas] juga tidak bisa dipegang pengerjaannya. Padahal, kunci dari gas itu adalah infrastruktur karena gas itu harus dialirkan terus. Dan yang paling mungkin terpakai terus adalah pipa,” katanya.

Menurutnya, interkoneksi region 1 (Sumatra bagian utara)-region 3 (Jawa Tengah) paling mungkin terjadi dengan infrasturktur pipa. Dia mencontohkan tersambungnya pipa gas Cirebon-Semarang, bukan hanya memberikan solusi kepada pelaku industri di Jawa Tengah, tetapi juga menyambungkan koneksi gas Sumatra dan Jawa. Produksi gas Blok A di Aceh sebesar 67,4 MMscfd juga akan menambah pasokan gas di region 1.

Suplai gas di region I (Sumatra bagian utara) bisa bertambah dari PHE NSO-NSB dan ENI Krueng Mane Ltd. Suplai gas di region 2 (Sumatra bagian tengah, selatan, dan Jawa Barat) menghadapi tantangan penurunan produksi gas Pertamina EP Aset II. Fasilitas FSRU Lampung dapat menjadi alternatif memasok gas di region tersebut. Namun, harga gas dari FSRU masih menjadi kendala karena dinilai masih terlalu tinggi. Ada beberapa proyek hulu migas yang strategis di region 2, seperti Bison, Iguana, Gajah Puteri dan pengembangan lapangan oleh Premier Oil dengan estimasi produksi gas sebesar 163 MMscfd pada kuartal 3/2019.

Selain itu, ada potensi suplai pasokan gas East Natuna sebesar 1.000 MMscfd dan PetroChina untuk Lapangan Tiung di Sumatra bagian tengah dan selatan mencapai 100 MMscfd pada 2027. Region 3 (Jawa Timur) bisa mengandalkan pipa gas ruas Semarang-Gresik dengan pasokan gas dari Lapangan Jambaran-Tiimg Biru. Direktur Utama & CEO PT Bakrie & Brothers Tbk. Bobby Gafur Umar mengatakan bahwa pembangunan pipa gas harus melihat aspek keekonomian, yaitu dari sisi suplai dan permintaan. 

“Kalau dilihat dari suplai memang surplus banyak, tetapi kalau permintaannya tidak ada, itu yang sekarang bahwa sedang diidentifikasikan di Kalimantan Timur dan Kalimantan Selatan [proyek pipa gas Bakrie,” katanya.

Menurutnya, konsep pembangunan pipa gas tidak jauh berbeda dengan jalan tol, yaitu potensi pelanggan dan pengguna fasilitas tersebut.

“Pak Wakil Menteri Arcandra Tahar bilang pasokan gas tidak akan terjadi kalau tidak ada infrasturktur. Nah, kami sekarang sudah siap dengan suplai, sampai akhir tahun diharapkan sudah bisa diketahui permintaan gas dari konsumen.

Bisnis Indonesia, Page-24, Tuesday, Oct 2, 2019

Friday, March 24, 2017

PetroChina Supplying Power Plant


PetroChina International Jabung Ltd. Ready delivers gas 5 million cubic feet per day of Golf South / West Betara to meet the needs of a gas power plant in Tanjung Jabung Barat, Jambi. 


PetroChina Jabung Ltd.

    Field Manager of PetroChina Jabung Ltd. John Halim said that the gas pipeline will be supplied if the power plant is ready. "Essentially, our supply is ready, just open the tap," he said.

John explained that the gas as much as 5 million cubic feet per day (MMSCFD) prepared it is subject to government approval is predicted to run power plants with a capacity of 25 megawatts (MW). 


SKK Migas

    According to him, the gas supply has been reserved by SKK Migas-PetroChina since 2012. However, during this time the untapped natural gas. "Our reserves of gas are expected to replace the supply from the Field Ripah broken recently for power plants operated by PT Tanjung Jabung Power," he said.

John said the current supply of the gas from Ripah volume continued to decline and is now no longer possible to be able to meet the plant's needs. PetroChina did not resume gas supply to Tanjung Jabung Power since Sunday (19/3) as the condition of flare gas from the field Ripah down naturally. Moreover, the rate of decline in gas production from the field Ripah also difficult to predict.

Cessation of gas supplies from the Field Ripah was not made suddenly but previously has been communicated formally to the manager of Gas Power Plant Tanjung Jabung Power, with intended also to the Regent Tanjung Jabung Barat.

Until now there were several gas purchase agreements signed by PetroChina with a number of companies to meet needs in the country. PetroChina gas allocating each 5 MMSCFD in Tanjung Jabung Barat and Tanjung Jabung Timur 10 MMSCFD to be managed at the provincial and district government through PT Jambi Jambi International Indoguna.

"All of the gas allocation as well as a form of awareness and contribution of SKK Migas-PetroChina to meet the gas demand in the regions concerned.

Bisnis Indonesia, Page-30, Friday, March 24, 2017

Monday, October 17, 2016

PIEP Production Up 7.3%




PT Pertamina International EP (PIEP) recorded oil and gas production of 122,600 barrels of oil equivalent per heart in the third quarter of 2016 up 7.3% compared to the same period last year 113,600 boepd.

Pertamina International EP is a subsidiary of PT Pertamina (Persero) which carries out oil and gas exploration and exploitation activities abroad.

International Director of Pertamina Slamet Riadhy said the achievement came from oil production of 86,700 BPD and gas of 207 million cubic feet per day (MMscfd). Oil production in quarter III / 2015 78,400 BPD and gas 204 MMscfd.

He explained, this year's additional production came from and the development of oil and gas blocks in Algeria which added 2,500 BPD of oil. Through the application of water injection in Iraq, the production of 4,000 BPD of oil increased and the practice of gas and water injection in Malaysia contributed 3,000 barrels equivalent per day / boepd.


Oil production in Iraq comes from the West Qurna 1 Field with 178 active wells. In this block, ExxonMobil controlled 32.69% participating shares and became operator, PetroChina 32.69%, Shell 19.62%, Pertamina International 10%, and Iraq's South Oil Company (SOC) 5%.



Pertamina International EP (PIEP) controls a 65% stake in MLN Field, Algeria. In addition, PIEP also has a participation stake in EMK Field (Algeria) 16.9%, while Sonatrach (37.74%), Anadarko (18.13%), Talisman (9.10%), ENI (9.065%), and Maersk (9.065%).


Production contributions in Malaysia came from activities in Block K, Block Kikeh, SNP Block, SKS O9 Block, and SK 311. Block in that block, Pertamina partnered with Murphy Oil, Petronas, ConocoPhillips, and Shell.


This increase in production was supported by the average increase and Project Phase 4 Development in Algeria by 2,500 BPD, water injection in Iraq which increased by around 4,000 BPD, and gas and water injection in Malaysian oil and gas fields increased by around 3,000 boepd.

So far, the average PIEP production of 123,000 boepd, which is 87,000 BPD of oil and gas 215 MMscfd. The company must ensure that production stays at 120,000 boepd until the end of this year in accordance with the company's target.

Bisnis Indonesia, Page-30, Monday, Oct 17, 2016.